approved contract

Aug 23, 2023

Description

Authorize to amend a sole source Cooperative Project Agreement with the University of New Hampshire, Sponsored Program Administration, Durham, NH (originally approved by G&C on 8/17/22, Item #41), for the NHDES Stormwater Manual Update project, by: extending the completion date from August 31, 2023 to June 30, 2024; increasing the contract award amount by $20,000 from $139,881 to $159,881; and revising the scope of work to include additional deliverables. Effective upon G&C approval through June 30, 2024. 100% Federal Funds

Amount
$159,881
$20,000, $139,881, $159,881
Funding Source
100% Federal Funds
Effective Dates
August 31, 2023 — June 30, 2024
Vote Record approved
Motion by Kenney, seconded by Stevens authorized
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes