approved contract late itemMay 31, 2023
Description
Authorize the Bureau of Construction to enter into a contract with Northeast Earth Mechanics, LLC., Pittsfield, NH, on the basis of a single bid of $974,213, for replacement of the bridge on NH 107 over Freese’s Pond in Deerfield, NH (2) Further authorize a contingency in the amount of $48,710.65 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through May 31, 2024. 100% Other Funds
Amount
$974,213
$974,213,, $48,710.65
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Other Funds
Vote Record
approved
Motion by Wheeler, seconded by Kenney acted as follows
Joseph Kenney
(R)
yes
Cinde Warmington
(D)
yes
Janet Stevens
(R)
yes
Ted Gatsas
(R)
yes
Dave Wheeler
(R)
yes