Item 22
approved contractOct 2, 2019
Description
Authorize the Bureau of Construction to enter into a contract with New England Signal Systems Inc., Northwood, NH, on the basis of a low bid of $511,753.50 for conversion of permissive left turns to flashing yellow arrow signal configuration. (2)Further authorize a contingency in the amount of $25,587.68 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through November 6, 2020. 100% Federal Funds.
Amount
$511,754
$511,753.50, $25,587.68
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Prescott, seconded by Volinsky acted as follows
Michael Cryans
(D)
yes
Andru Volinsky
(D)
yes
Russell Prescott
(R)
yes
Ted Gatsas
(R)
yes
Debora Pignatelli
(D)
yes