Authorize the Bureau of Construction to enter into a contract with Northeast Traffic Control Services, Plymouth, MA, for horizontal curve signs on all state owned roadways in maintenance District 1, on the basis of a low bid of $792,465. (2)Further authorize a contingency in the amount of $31,698.60 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through August 14, 2020. 100% Federal Funds.

Amount
$792,465
$792,465, $31,698.60
Funding Source
100% Federal Funds
Vote Record approved
Motion by Volinsky, seconded by Prescott acted as follows
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes