Meetings / Sep 13, 2017 / Item 19

Item 19

approved contract late item

Sep 13, 2017

Description

Authorize the Bureau of Construction to enter into a contract with Ray’s Electric and General Contracting Inc., Berlin, NH, for placement of a gateway sign, an interpretive sign, benches, historical district street signs, landscaping, and construction of a playground area in Berlin, on the basis of a single bid of $228,579. (2)Further authorize a contingency in the amount of $22,857.90 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through June 29, 2018. 100% Federal Funds.

Amount
$228,579
$228,579, $22,857.90
Funding Source
100% Federal Funds
Vote Record approved
Joseph Kenney (R) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_19.pdf Open in new tab →