Item 65
approved transfer late itemSep 13, 2017
Description
Authorize to enter into an agreement with F.L. Merrill Construction Inc., Loudon, NH, for construction services on the Suncook River Mitigation Project, in the amount of $2,292,545. 61% Capital (General) and 39% Transfer from DOT Funds. (2)Further authorize a contingency in the amount of $343,882 to cover unforeseen conditions and work that may occur during construction of the Suncook River Mitigation Project, bringing the total to $2,636,427. Effective upon G&C approval through April 30, 2018. 100% Capital (General) Funds.
Amount
$2.6M
$2,292,545, $343,882, $2,636,427
Department
DEPARTMENT OF ENVIRONMENTAL SERVICES
Funding Source
61% Capital (General) and; 39% Transfer from DOT Funds; 100% Capital (General) Funds
Vote Record
approved
Joseph Kenney
(R)
yes
Andru Volinsky
(D)
yes
Russell Prescott
(R)
yes
Christopher Pappas
(D)
yes
Dave Wheeler
(R)
yes
Documents (1)