Item 178
approved contract consent calendar late itemJun 18, 2014
Description
Authorize the Bureau of Construction to enter into a contract with R.S. Audley Inc., Bow, NH, for replacing the structurally deficient bridge carrying US 4 over both the Mascoma River and the Northern Rail Trail Corridor in Lebanon, on the basis of a low bid of $8,943,584.35. (2)Further authorize $447,179.22 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through June 24, 2016. 100% Federal Funds.
Amount
$8.9M
$8,943,584.35, $447,179.22
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Pappas, seconded by Pignatelli
Joseph Kenney
(R)
yes
Colin Van Ostern
(D)
yes
Christopher Sununu
(R)
yes
Christopher Pappas
(D)
yes
Debora Pignatelli
(D)
yes
Documents (1)