Item 195
approved contract consent calendar late itemJun 18, 2014
Description
Authorize the Bureau of Construction to enter into a contract with Nelson Communications Services Inc., Center Conway, NH, for replacing an existing 36” corrugated metal culvert crossing NH Route 106 (Parade Road) in Laconia with a 60” plastic pipe, on the basis of a low bid of $163,473. (2)Further authorize a contingency in the amount of $16,347.30 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through September 26, 2014. 100% Federal Funds.
Amount
$163,473
$163,473, $16,347.30
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Pappas, seconded by Pignatelli
Joseph Kenney
(R)
yes
Colin Van Ostern
(D)
yes
Christopher Sununu
(R)
yes
Christopher Pappas
(D)
yes
Debora Pignatelli
(D)
yes
Documents (1)
Item_195.pdf