Item 65

approved contract consent calendar

Apr 23, 2014

Description

Authorize to amend a sole source agreement with Lakes Region Planning Commission, (originally approved by G&C on 11-9-11, item #84), to complete the Suncook River Fluvial Erosion Hazard Community Assistance project, by extending the completion date to June 30, 2015 from June 30, 2014. No Additional Funding. 100% Capital (General) Funds.

Vendor
Lakes Region Planning Commission, (originally approved by G&C on 11-9-11, item #84)
to complete the Suncook River Fluvial Erosion Hazard Community Assistance project, by
Funding Source
100% Capital (General) Funds
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_65.pdf Open in new tab →