Item 98
approved contract consent calendarApr 23, 2014
Description
Authorize the Bureau of Construction to enter into a contract with Stephens Marquis Associates Inc., Merrimack, NH, for a new fueling facility and removing the existing fuel tanks at the Andover, Franklin and Canterbury Sheds, on the basis of a low bid of $856,000. (2)Further authorize a contingency in the amount of $85,600 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through November 14, 2014. 100% Capital Budget Funds.
Amount
$856,000
$856,000, $85,600
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Capital Budget Funds
Vote Record
approved
Joseph Kenney
(R)
yes
Colin Van Ostern
(D)
yes
Christopher Sununu
(R)
yes
Christopher Pappas
(D)
yes
Debora Pignatelli
(D)
yes
Documents (1)
Item_98.pdf
Open in new tab →