Meetings / Feb 16, 2022 / Item 95

Item 95

approved contract late item

Feb 16, 2022

Description

Authorize to enter into a contract with HDR Engineering Inc., Manchester, NH, to perform an engineering evaluation and design the repairs or replacement of the three existing flood gates at Lakeport Dam in Laconia, in an amount not to exceed $122,399. Effective upon G&C approval through October 31, 2022. 100% Capital (General) Funds.

Amount
$122,399
$122,399
Vendor
HDR Engineering Inc.
Manchester, NH
Funding Source
100% Capital (General) Funds
Vote Record approved
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_95.pdf Open in new tab →
← Back to Feb 16, 2022 meeting